Al Hidd IWPP - Bahrain

A plant of 272,760 m3/day (60 MIGD) provided with several ancillary equipment and facilities

Scope of work

Engineering, procurement, construction and commissioning of 10 desalination units of 27,276 m3/day (6 MIGD) each, together with: 3 x 250 t/h auxiliary boilers and gas receiving station, blackstart generator, CO2 plant, limestone based re-mineralisation plant, electrochlorination plant, sea water pumps and sea water filtration system, reject culvert, power water & gas fiscal metering systems, industrial buildings and ancillary equipment.

Contract data

Client: Hidd Power Company ; End-user:  Electricity and Water Authority
Contract awarded in the frame of Al Hidd Independent Water & Power Production project

Key dates

Limited Notice To Proceed
Final Notice To Proceed

Jan 06
Apr 06

First water
Completion dates

May 07
Jun 07 - May 08

Main quantities

Sidem Management & Supervision Team at peak
On-Site Erection Personnel at peak
Civil Works, Site Erection, E&I & Mechanical productive manhours
Duplex / Stainless Steel Supply
Aluminium Brass tubes
Titanium Tubes
Piperacks

150
2,000
6,000,000
6,000 t
6,000 t
300 t
1,500 t

Share