Al Khobar 2 - Saudi Arabia
MSF-BR - 10 units of 26,700 m3/day (267,000 cubic meters daily production)
Scope of work
Engineering, procurement, construction and commissioning of 10 units of 26,700 m3/day each (267,000 m3/day in total). The units are based on the MSF with brine recirculation process.